Utility Non-Wires Alternative Worksheet
Scope a distribution non-wires alternative study
Which constrained feeder, transformer or substation would a local resource need to support, at what electrical location, and during which dated load intervals? Start with the utility-defined need, then describe the proposed resource duty and the evidence still to obtain.
This blank worksheet helps utility planners frame whether distributed generation is worth further study as a non-wires alternative (NWA). It does not establish engineering approval, operating instructions, feasibility, savings or upgrade deferral. The utility determines the planning criteria and required studies.
Download the distribution constraint-to-duty worksheet (PDF)
Four US Letter portrait pages with 22 blank editable text fields. Print at actual size, or download and open in a PDF reader that supports saving form fields. Save a copy, close it and reopen it to check your entries before sharing. Browser preview support varies. Keep entries concise; attach referenced interval profiles, drawings and cost evidence separately.
How to use the worksheet
Keep the three records distinct: utility-defined need, proposed resource duty, and evidence still to obtain. Identify units, dates, revisions and measurement boundaries. Leave unknown values blank and list the missing evidence with an owner and due date. Proposed output at a connection point must be mapped to relief at the constrained asset by the utility study; nameplate capacity alone is not proof of useful net contribution.
Use one worksheet per constrained asset and candidate configuration. The prompts below are the same ones included in the PDF.
1 / Utility-defined need
Use utility planning inputs first. This worksheet scopes an engineering discussion; it is not engineering approval or an operating procedure. Leave unknowns blank and record them on page 4.
Utility, record date and planning owner
Utility / project reference; planner and team; worksheet date / revision.
Constrained asset and electrical location
Asset ID / type, substation / feeder / segment, voltage and phase; constraint type; candidate connection point and topology / one-line revision.
Utility planning criterion and system condition
Applicable rating / limit and units; normal or contingency configuration; limiting condition, affected customers and study reference.
Dated overload window and need-by date
Study years; season / dates, start-end times and time zone; interval length, hours per event, events per year and consecutive-day exposure; in-service deadline.
Load forecast basis and uncertainty
Dated interval dataset / forecast revision; measured vs forecast status; growth, weather, existing DER and electrification assumptions; sensitivity cases.
Required net contribution at the constrained location
Time-varying relief and units (kW / kVA / A as applicable); required duration / energy; reserve or margin; utility study mapping connection-point output to asset relief.
2 / Proposed resource duty
Describe a candidate resource or portfolio separately from the need. Nameplate capacity alone does not establish net relief at the constrained asset. Proposed duties require configuration-specific evidence.
Candidate configuration and measurement boundary
Technology / portfolio, configuration revision, location and owner; gross output, auxiliaries / site load and proposed net export or load reduction boundary.
Dispatch duty over the overload window
Proposed net output profile, startup / notification time, ramp and minimum output; sustained duration, repeat calls and recovery / replenishment between events.
Availability and limiting conditions
Availability during every required interval; weather / ambient limits, planned maintenance, forced outages, derating, resource life and degradation assumptions.
Supply and infrastructure dependencies
Fuel / feedstock or stored-energy inventory and replenishment; water, auxiliaries, access and supply continuity during the required duty; permits and operating-hour limits.
Control, dispatch authority and performance verification
Who calls and confirms delivery; communications / telemetry and metering boundaries; dispatch priority against other services; verification records and responsible party.
Duty-to-need match still to demonstrate
Requested tests / models and conditions for output, duration and repeat duty; mark each assertion measured, estimated, projected or planned; cite source and revision.
3 / Failure, fallback and delivery constraints
Record arrangements and questions for utility review, not switching steps or settings. A candidate must be studied against the actual network and underperformance scenarios.
Failure and underperformance scenarios
Loss of unit / portfolio member, fuel or stored energy, communications or dispatch; correlated outages; unmet relief and resulting asset exposure for each case.
Fallback arrangement and responsible owner
Proposed alternate capacity / utility mitigation, activation lead time, duration and limits; who confirms sufficiency; contingency-study reference and unresolved gaps.
Interconnection and electrical constraints
Connection / export limits, protection, voltage, thermal / fault-duty impacts, power quality, metering and controls; required studies, mitigations and approval dependencies.
Site, infrastructure and schedule constraints
Land / rights, civil works, access, fuel / water / electric service, environmental permits and network works; procurement, construction and commissioning lead times vs need-by date.
Commercial responsibility and review gates
Ownership / dispatch contracts, availability and performance obligations, monitoring and remedies; utility engineering / procurement owners; evidence required before the next decision.
4 / Comparison inputs and evidence to obtain
Compare alternatives against the same utility need, reliability criteria and dated analysis basis. No savings, upgrade deferral or feasibility finding is established by completing this worksheet.
Conventional baseline and other alternatives
Named upgrade / other options; scope, estimate source / date, in-service timing, useful life and residual value; any candidate deferral period to study, not assume.
Project-specific costs and economic basis
Capital / connection / site works, fuel / energy, O&M, controls, contracts, backup, replacement / removal; study period, discount rate, price basis and sensitivities; source / confidence.
Benefits, risks and comparable analysis still needed
Potential avoided costs and timing; permitted additional services without double counting or dispatch conflicts; reliability / delivery risks; shared cost-benefit method and evidence gaps.
Evidence still to obtain: item / owner / due date
List missing interval studies, forecast cases, location-to-relief model, duty / failure evidence, interconnection scope and dated quotes; source / revision / status for each item.
Next engineering discussion
Open decision / question, participants and next review date. Summarize what must be obtained before deciding whether further NWA study is warranted.
Discuss the specific constraint
Send your utility name, constrained asset or electrical location, dated overload window and the evidence gaps you want to discuss to resilient-power-works@brainer.one. Resilient Power Works takes a technology-agnostic approach: H2PWR Systems may be one candidate to evaluate, but its configuration-specific duty and site fit require evidence. Use your utility-approved secure channel for sensitive network, protection or customer information.
Outline the utility need separately from the proposed resource duty. Share only a non-sensitive summary.
- Utility / team and constraint type (no asset identifiers or network details)
- Overload window and required relief / duration (non-sensitive summary with units)
- Proposed resource duty and how net relief remains to be demonstrated
- Key evidence gap or question for discussion
Opens your email app with editable prompts. Nothing is sent until you send it. If no email app opens, use the email address above and these prompts.
Source references
The planning structure draws on EPRI's separation of system needs, technology adequacy, siting, multi-year alternative comparison and contingency arrangements, and Berkeley Lab's explanation that locational value depends on resource capability and potential avoided costs at the specific grid location. The worksheet is RPW's blank discussion aid, not an EPRI or Berkeley Lab form or endorsement.
- EPRI, Integrating Non-Wires Alternatives into Utility Planning, 2023 Research Guide (3002027412), Aug. 2023; especially pp. 6-7..
- Berkeley Lab, Value of Distributed Energy Resources Largely Depends on Three Things: Location, Location, Location, Feb. 12, 2021 (primary explainer)..
The complete eight-page EPRI 2023 guide and the complete Berkeley Lab primary explainer webpage were reviewed for this resource. Confirm current utility requirements and project inputs; these sources do not validate any candidate resource.