Distributed Generation Microgrid Planning for Utilities

Distributed generation microgrid planning starts with the service a utility must preserve, the loads inside the proposed island and the required outage duration. Define grid-connected, transition, islanded and reconnection duties before comparing generation options. Then evaluate generation, controls, protection and supporting infrastructure as one operating system. A generator’s rated output alone does not establish whether the microgrid can carry its critical loads through a grid outage.
Use the free outage-load calculator to compare running peak with load energy for one continuous load and one concurrent added-load block. These are load-side requirements, not equipment sizes. The walkthrough below changes one outage assumption; carry the results into the operating-mode, protection and supply checks that follow.
Start distributed generation microgrid planning with a service requirement
Describe the service the microgrid must preserve before selecting equipment. A feeder section serving a water facility has different restoration priorities from a substation support project or a customer campus.
If the project also targets a distribution overload, use the distribution constraint-to-duty worksheet to record the named constrained feeder, transformer or substation, the dated overload window and the required net contribution at that asset. Keep this grid-connected duty separate from the critical-load outage requirement; the worksheet frames further utility study, without establishing feasibility or upgrade deferral. For the evaluation behind that record, see distributed generation as a non-wires alternative: electrical location, useful net relief, availability, fallback and comparable economics.
A critical-load register should specify the function to preserve, the electrical load that supports it and the conditions under which service is needed. Agree on priorities with facility operators and emergency planners: a load that looks discretionary to the utility may support a critical process downstream.
Sandia’s Microgrid Conceptual Design Guidebook, particularly its critical-load and design-basis-threat modules, recommends ranking functions against outage scenarios and examining infrastructure dependencies. The following register structure applies that approach to a utility site:
- Function and priority tier. Identify the served process, circuit or equipment group, its owner and the consequence of losing it. Agree on tiers such as service that must be preserved, service that may be restored after a defined delay, and service that may be deferred or shed. These are site-agreed categories, not mandated reliability classes. Record the order for shedding and restoring loads, and who may change priorities as the event develops.
- Allowable interruption. Record the maximum interruption in seconds, minutes or hours, the deadline for restoring the function, and whether a controlled restart is acceptable. A high-priority load may tolerate a short break; another may require continuity support. Record any existing uninterruptible power supply and its supported load and verified runtime rather than assuming the microgrid transition meets that need.
- Time-varying demand. Record required running kW, operating windows, duty cycle and daily or seasonal variation. Separate the critical portion from the whole-building demand and identify loads that can run at different times. Use interval data to build an outage load profile; label estimates and their basis where measurements are missing. Calculate load energy in kWh by summing power multiplied by time for each interval. Annual energy consumption cannot establish peak power or transition requirements.
- Pickup and restart needs. Record motor-starting or transformer inrush data, abrupt load steps, reactive-power needs and equipment that must be energized first. Identify whether loads restart together after an interruption or can be picked up in stages. Supplement interval records with equipment data and higher-resolution measurements where needed. Running kW and outage kWh do not establish whether the resource mix can accept pickup; that requires electrical studies and an agreed acceptance-test scope.
- Dependencies and evidence. Identify controls, communications, cooling, water, auxiliary power and other services needed to keep the function operating or restart it. Record each dependency’s outage availability, evidence source, unresolved question and responsible owner. Include supporting loads in the register so they are not inadvertently shed while the process they support remains a priority.
Pair the register with named outage scenarios. For each, state the event, affected area, start time and season, required island duration, and which loads must operate during each period. Record starting resource conditions—such as available equipment, battery reserve and usable fuel inventory—separately from load requirements. State whether pipeline supply, fuel deliveries, water and communications remain available, when resupply is assumed, and the service required if it is delayed or unavailable.
NREL’s Microgrids for Energy Resilience, Sections 2.4, 2.6, 3.4.2 and 4.4.4–4.5, connects load priority, downtime thresholds, outage duration, fuel resupply and dynamic load behavior. Its defense-project examples inform this planning method; they do not set utility-site requirements. Agree on the required service for each scenario before comparing resource configurations.
Use the critical-load and outage-scenario worksheet guidance to record load priorities, interruption limits, time-varying demand, pickup needs and supply assumptions before a site discussion. Record evidence gaps and responsible owners alongside the requirements. The guidance includes a blank, fillable worksheet PDF for capturing those inputs.
Define the electrical boundary and operating modes
Mark the proposed island boundary on a one-line diagram. Identify the isolation point, included loads, existing generation, transformers, switching devices and possible backfeed paths.
Evaluate four operating stages: grid-connected operation, transition to an island, islanded operation and reconnection. The NREL guide to interconnection rules and IEEE Standard 1547 explains that intentional islands require additional technical and operational coordination, including protection and control agreements.
For each stage, answer these questions:
| Operating stage | Decision to resolve |
|---|---|
| Grid-connected | Will the resource export, follow site load or provide an agreed grid service? |
| Transition to island | Which loads can tolerate a break, and which require continuity support? |
| Islanded | Which resource establishes voltage and frequency, and how are loads prioritized? |
| Reconnection | Who authorizes return to parallel operation, and how is synchronization controlled? |
A parallel-operation interconnection approval should not be treated as approval for every islanded operating arrangement. Establish the permitted modes with the relevant utility teams early.
Use the distributed generation interconnection evidence matrix to turn those mode decisions into a review request. It distinguishes configuration-specific equipment evidence, proposed operating modes, protection and communications information needed before review, and acceptance records obtained later under the agreed site-test scope.
Use the microgrid operating-boundary concept and checklist to map generation, storage, critical loads and supporting supplies within a candidate island. Its responsibility questions help identify who must resolve dispatch, transitions and restoration before the design scope is fixed.
Separate power capability from endurance
Power is the rate of electrical delivery, measured in kilowatts or megawatts. Energy is delivery accumulated over time, measured in kilowatt-hours or megawatt-hours. The microgrid needs both sufficient instantaneous capability and a credible energy supply for the chosen outage scenario.
Consider a planning exercise: a critical-load island requires 300 kW continuously for 24 hours, with an additional 150 kW pumping load for two of those hours. Its load energy is:
300 kW × 24 h + 150 kW × 2 h = 7,500 kWh.
Its running peak is 450 kW. Those figures do not yet include generation auxiliaries, electrical losses, motor-starting demand or operating reserves. They establish separate questions: can the system serve the peak, and can it supply 7.5 MWh of load energy through the event?
Follow the worked outage record and running-duty diagram to carry this exercise into the worksheet, with pumping assumed at elapsed hours 8–10. The record keeps those assumptions and the unresolved interruption, pickup, supply and equipment evidence separate from the running-load arithmetic.
Model unfavorable conditions as well as the expected case: low renewable output, a delayed fuel delivery, unavailable equipment or an outage beginning during maintenance. State which contingencies the design is required to cover rather than adding an unexplained margin.
Try changing one outage assumption
Open the free outage-load calculator to vary one continuous running load and one concurrent added-load block. The walkthrough below changes only outage duration so you can see why running peak and load energy are separate requirements.

- Enter the four assumed inputs: Continuous running load (kW): 300; Concurrent added running load (kW): 150; Added-duty block duration (hours): 2; Total outage duration (hours): 24. Change only total outage duration to 12 hours. Keep one concurrent two-hour added block entirely within the outage; the calculator does not assign its timing or repeat it each day.
- Read the result: running peak stays 450 kW, the highest concurrent running demand (300 + 150). Load energy falls from 7,500 kWh (7.5 MWh) to 3,900 kWh (3.9 MWh): (300 kW × 12 h) + (150 kW × 2 h) = 3,600 + 300 = 3,900 kWh. Energy is running load accumulated over time, not the running peak.
- Ask: What service must continue, how much interruption is allowed, and which load records support these assumptions? Use Copy discussion summary or Open email draft with current assumptions to carry the current values into a discussion with RPW. Review and edit the draft before sending; nothing is sent automatically. Use non-sensitive assumptions only and keep confidential site details in an agreed secure channel. The company contact is below.
These load-side calculations do not size equipment or establish storage, fuel requirements or H2PWR Systems runtime. Pickup/inrush, transfer/restart, losses, auxiliaries, reserves and supply capability remain unresolved—not assumed zero.
Study controls and protection in both network conditions
Grid-connected and islanded systems can have different fault-current and voltage-control behavior. Protection settings and dispatch logic must be evaluated for the actual resource mix; they cannot simply be copied from the existing feeder configuration.
The engineering scope should identify:
- The source of voltage and frequency reference in an island.
- Resource coordination during load steps, load shedding and generation trips.
- Fault detection, isolation and relay coordination in each mode.
- Grounding arrangements and their behavior after island formation.
- Operation during communications loss or controller failure.
- Black-start and restoration sequences, where required.
Document acceptance tests for those functions. “Dispatchable” describes controllable output; it does not, by itself, establish black-start capability or uninterrupted transfer.
Include fuel, water and maintenance in the resilience boundary
Generation equipment may remain intact while its supporting infrastructure becomes unavailable. Review fuel delivery, on-site inventory, water supply, treatment systems, auxiliary power and access for maintenance under the same event used to evaluate the electrical network.
NREL’s Battery Storage for Resilience identifies critical load and anticipated outage duration as key selection inputs and discusses the limits imposed by stored fuel and disrupted fuel supply chains. The relevant question is how the proposed resource will be supplied at this site during the event, not whether its fuel is generally available in the region.
Develop an operations plan covering staffing, inspections, consumables, spare parts and periodic islanding tests. Assign responsibility for each function, including equipment supplied by different vendors.
Compare complete project scopes
Compare alternatives against the same service requirement and outage scenarios. Include generation, storage where needed, controls, switchgear, interconnection work, civil works, fuel and water infrastructure, permits, commissioning and ongoing support.
Distinguish capital cost from lifecycle cost. Maintenance outages, replacement components, auxiliary consumption and required staffing belong in the comparison alongside fuel costs. Equipment-only quotes with different scope boundaries are not comparable project costs.
For complementary resource duties, see batteries versus generators for microgrid resilience. For product-specific site inputs, see evaluating H2PWR Systems for a utility site.
Resilient Power Works takes a technology-agnostic approach to this evaluation: its site-selection discussion explicitly recognizes that another generation solution may be better for a particular application. H2PWR Systems™ may be considered within that comparison, with its proposed configuration assessed against the utility’s operating requirements.
Prepare a microgrid application discussion
Use the Utility Application Discussion handout (PDF) to organize the service requirement before a technical conversation. For a microgrid, include the proposed electrical boundary, critical-load profile, outage target and known site constraints.
Send your utility name, site or location, and operating need with those inputs to resilient-power-works@brainer.one to discuss which generation options merit site-specific evaluation.
Source references
- Sandia National Laboratories, Microgrid Conceptual Design Guidebook (March 2022): critical-load prioritization, infrastructure dependencies and site-specific conceptual design.
- NREL, Microgrids for Energy Resilience: A Guide to Conceptual Design and Lessons from Defense Projects (2019), Sections 2.4, 2.6, 3.4.2 and 4.4.4–4.5: load priorities, interruption thresholds, outage duration, resupply and load modeling; defense examples are adapted to utility planning.
- NREL, A Guide to Updating Interconnection Rules and Incorporating IEEE Standard 1547 (2021): intentional-island configurations and technical and operational coordination.
- NREL, Battery Storage for Resilience (2021): critical loads, outage duration and energy-supply constraints.
- Resilient Power Works, Locational Benefits & Situational Analysis: RPW’s technology-agnostic approach and site-evaluation considerations.
RPW main website ↗