Free Outage-Load Calculator: Running Peak & Energy
How much running power and load energy does your outage scenario require? Adjust four assumptions below to calculate running peak in kW and load energy in kWh or MWh. Free to use, without signup.
Calculate outage running peak and load energy
Enter one continuous load and one concurrent added-load block within the outage. Results update as you type. This is load-side arithmetic, not equipment sizing or a full time-varying site profile.
Use non-sensitive assumptions only. Editing keeps inputs in this page’s memory; this site does not save them in a record or send them to RPW. You can deliberately copy a link or open an email draft to share them.
Served throughout the assumed outage.
Added to the continuous load during one block.
One block, entirely within the outage; no timing is assigned.
The period of intended running-load service.
Running peak: 450 kW. 300 + 150 = 450 kW during the added-duty block.
Load energy: 7,500 kWh = 7.5 MWh.
Continuous load: 300 kW × 24 h = 7,200 kWh.
Added load: 150 kW × 2 h = 300 kWh.
Total: 7,200 + 300 = 7,500 kWh; divide by 1,000 for MWh.
Load-side running demand and energy only. Pickup/inrush, allowable interruption, transfer/restart, losses, auxiliaries, reserves and supply capability remain unresolved—not assumed zero. These results do not size equipment or infer storage, fuel requirements, resource runtime or H2PWR Systems capability.
Share this calculation with a colleague
Copy a link to include only the four valid numeric assumptions after the URL’s #. Opening it restores those assumptions and recalculates the results. The fragment is not sent in the page request, but anyone with the link can read it, and it may remain in browser history or the channel where you share it. Do not include sensitive information.
Editing does not update the address. A shared link reloads its original assumptions; a page without shared assumptions reloads the worked example. Reset clears shared assumptions from this address.
Discuss these outage-duty assumptions
If you choose to open a draft, the current valid inputs, running peak, load-energy arithmetic and unresolved evidence pass to your email app in an email link. Nothing is sent until you send it. Add your utility or team, required service, allowable interruption and next question.
Review and edit in your email app before sending. If no email app opens, use the copy controls and email resilient-power-works@brainer.one. Keep sensitive site, network, protection and customer information in your utility-approved secure channel.
Outage-load calculator usage answers
What do the four calculator inputs mean?
Continuous running load (kW) is served throughout the outage. Concurrent added running load (kW) is extra demand during one added-duty block. Added-duty block duration (hours) is the total length of that single block, not a daily repeat; no start time is assigned. Total outage duration (hours) is the intended service period. Enter finite, nonnegative numbers; the added block must fit within the outage. Results update as you type.
What is the difference between running peak kW and load energy kWh?
Running peak is the highest simultaneous running demand: continuous kW plus added kW when the added block has positive duration. Load energy accumulates over time: continuous kW × outage hours + added kW × block hours. Divide kWh by 1,000 for MWh. A zero-hour block contributes no added demand or energy; a zero-hour outage has zero load energy and no defined running peak.
How does changing outage duration affect the results?
With both loads and a positive added-block duration fixed, changing a positive outage duration changes continuous-load energy, not running peak or added-block energy. For the assumed 300 kW continuous load and 150 kW added for one 2-hour block, a 24-hour outage gives 450 kW and 7,500 kWh; 12 hours gives 450 kW and 3,900 kWh. The block still must fit within the outage; it does not repeat as the outage grows.
Can these results size a generator, battery or H2PWR System?
No. They describe load-side running demand and energy, not equipment capacity, storage or fuel requirements, or resource runtime. Pickup/inrush, allowable interruption, transfer/restart, losses, auxiliaries, reserves and supply capability need separate evaluation; they are unresolved, not assumed zero. Use the planning worksheets below to record evidence gaps for a site-specific study. No H2PWR Systems capability is inferred.
Critical-load planning worksheets
Record load priorities, allowable interruption, time-varying demand, pickup needs and supply dependencies before a site-specific microgrid sizing study. These worksheets organize discussion inputs, not an operating procedure or engineering approval.
Three-page blank worksheet with 17 editable multiline fields. Use a PDF reader that supports forms, save a local copy and reopen it to check your entries. If a field becomes crowded, attach a continuation keyed to the field and load/scenario ID. Download the editable Word worksheet (DOCX).
Follow a worked outage record
Start with the microgrid planning article’s 24-hour outage exercise: 300 kW continuously, plus 150 kW of pumping for two hours while the continuous load remains served. The worked record shows how to carry these inputs into the blank worksheet and identify what still needs review.
This is an assumed planning exercise, not a measured utility project. The values describe load-side running demand and energy; they do not establish generation capacity, storage or fuel requirements, resource runtime or H2PWR Systems capability.
Four-page completed reference record: assumptions and arithmetic, followed by entries for all 17 worksheet prompts. Use the existing blank worksheet for your own site, replacing the exercise assumptions with site requirements and evidence.
Assumptions to carry with the record
- Scenario CL-24 uses a 24-hour outage. Hours are elapsed from outage start, not calendar times; no date, season, hazard or time zone is assigned.
- L1 and L2 are bookkeeping IDs for grouped loads at a notional critical-load boundary, not identified site circuits. L1 is 300 kW continuously; L2 adds 150 kW of pumping concurrently for one two-hour block. No other loads or variability are represented.
- The calculation counts intended running-load service, without assuming successful transfer or restart. Generation auxiliaries, electrical losses, motor-starting demand and operating reserves are unquantified, not zero.
- Pumping is placed at elapsed hours 8–10 to make the duty visible. This added scheduling assumption is not a required dispatch schedule or measured operating pattern.
- Running levels are idealized. The interval boundaries do not show validated ramp rates, transfer performance, motor-start demand or restart behavior.
Read the running duty and load energy
Download the running-duty diagram (PNG) · Download the vector diagram (SVG)
| Elapsed hours | Running load | Interval load energy |
|---|---|---|
| 0–8 (8 hours) | 300 kW continuous | 300 × 8 = 2,400 kWh |
| 8–10 (2 hours) | 300 + 150 = 450 kW | 450 × 2 = 900 kWh |
| 10–24 (14 hours) | 300 kW continuous | 300 × 14 = 4,200 kWh |
Running peak: 450 kW. The highest concurrent running demand is 300 + 150 kW. It is not a pickup or inrush rating.
Load energy: 7,500 kWh = 7.5 MWh. 300 kW × 24 h + 150 kW × 2 h = 7,500 kWh; equivalently, 2,400 + 900 + 4,200 kWh.
Keep unresolved evidence separate
Use the worked record to distinguish an assumed load input from a requirement or demonstrated capability. Leave the following questions open until the responsible site or equipment team supplies evidence; do not substitute the 450 kW running peak or 7.5 MWh load energy for these answers.
- Service and interruption: confirm priority owners, allowable interruption, transfer/restart limits and any no-break requirement.
- Pickup and electrical behavior: obtain motor-start/inrush, starting method, kVA or power factor, voltage/phase and sequence evidence; review controls, protection and voltage/frequency response.
- Supply and dependencies: establish initial fuel/feedstock and water availability, resupply and no-resupply cases, auxiliary power, communications, staffing and common-cause event impacts.
- Configuration-specific capability: account for losses and auxiliaries and verify equipment output, storage, runtime and transition evidence against the documented duty.
Record each gap with its affected load/scenario, evidence needed, responsible owner and target date. Then use the blank prompts below for your own site boundary and outage case.
How outage duration changes load energy
This fixed comparison supplements the elapsed-hour running-duty diagram. It does not change when you edit the outage-duty exercise above. Each assumed outage has a 300 kW continuous load and one concurrent 150 kW two-hour block, placed at elapsed outage hours 8–10 to match the existing diagram. Hours count from outage start; this is an assumed placement, not a prescribed operating schedule.
Download the outage-duration comparison (PNG) · Download the scalable outage-duration comparison (SVG)
Running peak is 300 + 150 = 450 kW in every case. The one added-duty block contributes 150 kW × 2 h = 300 kWh (0.3 MWh) once per outage. It is not repeated each day. Only continuous-load energy changes with duration.
| Assumed outage duration | Continuous-load energy | Added-block energy | Total load energy | Running peak |
|---|---|---|---|---|
| 12 h | 300 kW × 12 h = 3,600 kWh | 150 kW × 2 h = 300 kWh | 3,900 kWh (3.9 MWh) | 450 kW |
| 24 h | 300 kW × 24 h = 7,200 kWh | 150 kW × 2 h = 300 kWh | 7,500 kWh (7.5 MWh) | 450 kW |
| 48 h | 300 kW × 48 h = 14,400 kWh | 150 kW × 2 h = 300 kWh | 14,700 kWh (14.7 MWh) | 450 kW |
Load energy = (continuous kW × outage hours) + (concurrent added kW × added-block hours). Divide kWh by 1,000 to obtain MWh. Thus (300 × 12) + (150 × 2) = 3,900 kWh; (300 × 24) + (150 × 2) = 7,500 kWh; and (300 × 48) + (150 × 2) = 14,700 kWh. The continuous energy already covers the two-hour block, so do not add its 300 kW continuous component a second time.
These are load-side running levels and energy totals. Pickup/inrush and restart sequence, allowable interruption and transfer performance, supply availability and dependencies, and equipment evidence remain unresolved. Losses and auxiliaries are not included; their required values remain unresolved, not assumed zero. The comparison does not size generation, storage or fuel, establish H2PWR Systems capability, or demonstrate that any system can support these outage durations.
The prompts below match the PDF. Use one site boundary and named scenario per record. Keep units, dates and evidence references with each input; use additional copies for more loads or scenarios.
1. Define the service and interruption limits
Record one site boundary and named outage scenario. Use additional copies for more loads or scenarios; cross-reference load IDs. Mark unknowns and label every value measured, estimated or required. This worksheet records discussion inputs; it does not size resources, approve engineering or confirm H2PWR capability.
Site, boundary and record owner
Utility/site; electrical boundary or drawing reference; scenario ID; preparer, role and date.
Critical service and priority basis
What service must continue, who sets its priority, and what consequence defines unacceptable loss?
Load register - one line per load or group
Load ID; service; circuit/location; priority; maximum allowable interruption with units; basis/owner.
Conditional priorities and deferrable loads
Which loads may be deferred or shed, by whom, and under what scenario? Record proposed order only.
Transfer, restart and continuity requirements
By load ID: required transfer time, restart delay, manual actions and any no-break power requirement.
Existing backup evidence
By load ID: backup path, startup time, supported duration, test date/conditions and unresolved limits.
2. Record time-varying demand and pickup needs
Attach an interval record or reference rather than substituting a monthly bill or equipment nameplate for an outage load profile. Keep real power (kW), energy (kWh), apparent power (kVA) and current (A) distinct. Interval averages do not establish transient pickup capability.
Demand evidence and boundary
Load IDs; meter/file reference; date range, time zone and sampling interval; units; gross or net boundary.
Demand by time window
Load IDs; window/season; minimum, typical and peak demand with units; concurrent loads; evidence basis.
Demand changes during the outage
Scenario ID; loads added/removed; duty cycles, weather/occupancy/process assumptions and uncertainty.
Pickup events and sequence for evaluation
Load ID; proposed pickup order; running demand; step change; motor start/transformer inrush and duration.
Electrical and startup evidence still needed
Voltage/phase, kVA or power factor, starting method, equipment/test reference; distinguish data from estimates.
Pickup and transition review questions
What remains to be studied for controls, protection, voltage/frequency and restart? Name owner and evidence.
3. Define outage duration, dependencies and evidence gaps
Distinguish allowable interruption from total outage duration. Do not assume resupply survives the same event that causes the outage. Record separate cases with and without resupply when relevant; no duration here is a prediction of resource runtime.
Outage scenario and duration basis
ID; hazard; start time/season; duration and units with historical, assumed or required basis. Load IDs; service/reduced-duty windows; restoration requirements to evaluate.
Supply and resupply assumptions
Fuel/feedstock, water or other supply: initial availability; resupply timing/route/agreement; no-resupply case.
Common-cause dependencies
Pipeline, roads, communications, controls, auxiliary power and staffing: event impact; evidence; fallback gap.
Evidence gaps and follow-up
Unknown/input; document, measurement or study needed; responsible owner; target date; affected scenario.
Site discussion summary
Highest-priority service; controlling interruption limit; outage case; key uncertainty; requested next review.
Sources and context
Reviewed 24 November 2026. These prompts adapt federal-site and defense-microgrid guidance to a utility site discussion. The references are not a utility requirement or product endorsement. No source sizing rules or example project outcomes are adopted.
- PNNL-33549: The Technical Resilience Navigator (February 2023). Reviewed sections 2, 3.1.1.2 and 4.2: functions, loads, interruption limits, startup/runtime and energy/water inputs. Federal-site planning context; no runtime calculations adopted.
- NREL/TP-7A40-72586: Microgrids for Energy Resilience (2019; revised January 2020). Reviewed sections 2.4, 2.6, 3.1, 3.4.2, 4.3.1, 4.4.4 and 4.5: priorities, duration/resupply, interval data, pickup and electrical studies. Defense-project context; no generator sizing rules or example outcomes adopted.
Related planning and comparison
Use the microgrid planning article for the broader project boundary, the generation-options worksheet to compare resources against this same duty, and the interconnection evidence reader for electrical review questions. This record supplies inputs to those discussions; it does not replace their studies.
Discuss your site requirements
Send your utility name, site boundary, highest-priority service, outage scenario and key evidence gaps to resilient-power-works@brainer.one. Use your utility-approved secure channel for sensitive site or network information.
Resilient Power Works takes a technology-agnostic approach. H2PWR Systems may be one option to evaluate against the documented duty and configuration-specific evidence.
Outline the service you need to sustain and the outage duty you want to discuss. Share only a non-sensitive summary.
- Utility / team and general application
- Highest-priority service and allowable interruption
- Outage duration and running-load / pickup needs (include units; mark unknowns)
- Key evidence gap or question for discussion