Distributed Generation Interconnection Evidence
Request the site, equipment, operating-mode, protection, controls, study and commissioning information needed to scope a utility engineering review. Record evidence, open questions and the responsible owner for each category.
Use this blank request register to scope a site-specific distributed generation (DG) review. Request documents from the project team and confirm requirements with the serving utility. A recorded response is evidence received, not technical acceptance.
General U.S. distribution-interconnection planning guidance, not a utility application, compliance certification or permission to operate. The serving utility and governing authority determine applicable rules, adopted standard editions, settings, studies and approvals. This checklist gives no live switching or test-execution instructions.
Four-page blank checklist with editable evidence, question and owner fields. General planning guidance; the serving utility determines site-specific requirements and approvals.
How to use the request register
Enter the utility/site and location, project/contact, proposed application and operating need, candidate connection point, and preparer/date.
For each category, record the document ID/link, revision/date and relevant finding; label measured results, estimates, projections or plans. Record unresolved questions and the person responsible. Use an attachment register if more space is needed. Mark non-applicable requests with a reason; do not treat blanks as approval.
Download and save the PDF in a reader that supports form fields to retain your entries, or print it to complete by hand. All 26 editable fields are blank. The request checkboxes are for manual marks, not interactive PDF fields.
1. Candidate connection point and electrical boundary
- Site/location and feeder or substation identifier; proposed point of common coupling, service voltage/phase, metering and equipment ownership boundaries.
- Boundary drawing showing utility-side or behind-the-meter connection, existing DG/storage, served loads, and any proposed intentional-island boundary.
- Serving-utility application route, current technical manual/tariff and governing authority; record edition, effective date, application ID and utility reviewer. Confirm the applicable reference point for requirements.
General request scope [1, 2]; confirm site boundary with utility.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
2. Proposed equipment and configuration
- Equipment schedule: manufacturer/model, technology, unit count, nameplate kW/kVA, voltage, transformer data and inverter or machine interface; include existing parallel resources.
- Configuration-specific data sheets: net output boundary and auxiliary loads, reactive capability, fault-current contribution and models; identify operating conditions and any estimates.
- Applicable certification and type-test reports, tested model/firmware and limitations; identify gaps between tested equipment and the proposed installed system. Equipment certification alone is not site approval.
General request scope [1, 2]; evidence must match the proposed assembly.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
3. Permitted operating modes and export
- Mode schedule: grid-parallel, non-export/limited-export, standby and intentional islanding, where proposed. Identify proposed versus utility-permitted modes and the document authorizing each.
- Proposed import/export limits at the agreed measurement point, load/generation profiles, export-limiting design and evidence of response to load changes or loss of measurement/control.
- Functional descriptions and evidence for transitions, loss of grid and return to parallel service; distinguish unintentional-island protection from intentional-island operation. Identify decision authority and operating restrictions; do not assume non-export avoids review.
General request scope [1, 2]; proposed modes are not permitted modes until confirmed.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
4. One-line and protection information
- Revision-controlled one-line with connection point, transformers/grounding, conductors, metering, isolation/paralleling devices, protective devices and current/voltage sensing locations.
- Protection narrative and coordination evidence addressing faults/open phase, voltage/frequency response, unintentional islanding and utility reclosing; identify transfer-trip or other mitigation if required by the utility.
- Proposed setting files, function ownership and change-control process; identify utility-selected performance categories and enabled voltage/reactive-power functions where applicable. Record utility review status separately from vendor capability.
General request scope [1, 2]; utility determines required functions and settings.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
5. Controls and communications
- Control architecture: DG/plant or microgrid controller, utility interface, command authority/priority, control-power dependencies and documented behavior on communications/control loss.
- Required monitoring, alarms and set points; supported and selected protocol, point list, units, timestamps and interface test evidence. Identify the boundary between local DG interface and external utility communications.
- Utility-specific telemetry/availability requirements and responsibilities for network provision, access control, cybersecurity, firmware changes and maintenance. IEEE 1547 interoperability guidance does not by itself define the external network or cybersecurity requirements.
General request scope [1-3]; local interface capability is not a complete utility communications design.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
6. Relevant studies and mitigations
- Utility screening/study determination and required inputs. As applicable, request load-flow/voltage/thermal, short-circuit/protection, grounding, power-quality, islanding and dynamic/transition assessments.
- Study revision, model files, assumptions and evaluated scenarios: minimum/peak load, other DG, export limits, feeder configurations, and proposed island operation where relevant.
- Results, limitations, required upgrades/mitigations, responsible parties and unresolved conditions. Identify which configuration and modes were studied; ask whether later equipment, firmware, mode or site changes require re-review.
Planning questions derived from [1, 2]; utility selects study scope, models and acceptance criteria.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
7. Commissioning and acceptance evidence
- Agreed commissioning/acceptance plan: criteria, responsible parties, required inspections/witnesses, and evidence for protection, export controls, communications and any permitted island transitions.
- As-built one-line, installed equipment/firmware inventory, final settings and dated installation/commissioning reports with conditions, results, exceptions and corrective-action closure. Distinguish type tests from installed-system evidence.
- Utility acceptance and written authorization required before parallel operation, including remaining conditions; periodic test/maintenance records and change/retest obligations. A completed checklist or vendor test report does not authorize energization.
General request scope [1, 2]; confirm applicable IEEE 1547.1 edition and local test/witness requirements.
- Evidence received
- Document ID/link, revision/date and relevant finding.
- Open question
- Unresolved information or review needed.
- Owner / review date
- Responsible person and next review.
Reviewed sources and their scope
- [1] IEEE 1547-2018 — public IEEE SA scope/status page
Reviewed 23 Nov 2026: listed Active; links amendment 1547a-2020 and errata. Public scope reviewed, not the paid standard text. Confirm adopted edition and applicability locally.
- [2] NREL/TP-5D00-75290 — A Guide to Updating Interconnection Rules and Incorporating IEEE Standard 1547 (Oct 2021)
Reviewed 23 Nov 2026: sec. 1.4.1, 2.3, 2.4.3-2.4.4 and 3.3 (printed pp. 17, 25-29, 38-40, 42-43). General rulemaking/technical background, not this site's utility requirements.
- [3] NREL/TP-5D00-77959 — Informative Background on the Interoperability Requirements in IEEE Std 1547-2018 (Jul 2021)
Reviewed 23 Nov 2026: introduction and sec. 1 (printed pp. 1-7). Separates local interface capability from implementation, external communications and cybersecurity decisions.
Related planning readers and articles
Discuss your site requirements
Discuss your site requirements with Resilient Power Works. Send your utility name, site/location, candidate connection point and proposed operating need to resilient-power-works@brainer.one. Identify the evidence gaps you want to discuss; use your approved secure channel for sensitive drawings or protection details.
resilient-power-works@brainer.oneOutline the proposed operating need and the evidence still needed for utility review. Share only a non-sensitive summary.
- Utility / team and general application
- Proposed operating mode and connection arrangement (general description only)
- Review stage and missing equipment, protection, controls or study evidence (categories only)
- Key question for discussion