Microgrid Critical Load Sizing for Utilities

Microgrid critical load sizing starts with a defined outage service, not a percentage of a site's peak. Build an interval load profile for the functions that must keep running, then test peak kilowatts (kW) and outage energy (kilowatt-hours, kWh) against acceptable interruption, pickup and supply assumptions. That gives planners a resource-comparison duty, not a final equipment rating.
What does microgrid critical load sizing need to define?
A critical load is the demand needed to maintain an agreed service during a particular outage. Its priority depends on the service and acceptable interruption, not just the label on a circuit. Define the electrical boundary, outage duration and event assumptions, then separate loads that can wait from those that must continue.
The DOE's 2025 Microgrid System Project Development Checklist says outage survival duration and critical loads should reflect outage history and relevant threats such as severe weather. The Sandia 2022 Microgrid Guidebook's critical-load module, pp. 19–21 describes priorities as site- and community-specific and advises considering outage duration; its community-planning framework is a reference, not a utility mandate.
For each critical function, record:
- The service it supports, its operating owner and its electrical connection point.
- The longest interruption it can tolerate and the deadline for restoring it.
- Its running demand and when that demand occurs during the outage.
- Dependencies such as controls, communications, pumps, cooling or other auxiliary supplies.
Use interval data to capture kW and kWh
Kilowatts describe demand at a point in time; kilowatt-hours add that demand across time. A monthly energy bill or single site peak cannot show which loads must run together or when a critical circuit peaks during an outage.
DOE's 2025 checklist says hourly kW data is typically used, subhourly intervals are preferred, and three years of data can help identify annual changes and unusual trends. Use the best available interval records, identify which circuits they cover, and label estimates or gaps instead of treating them as measured values.
Map each load to the one-line diagram before adding it to the islanded total. DOE notes that critical loads spread across multiple feeders can require controllable breakers, communications infrastructure and more complex control sequences. A critical-load priority does not by itself prove that those circuits can be isolated and served together.
Work through an eight-hour outage profile
Suppose a fictional water-utility site is screening an eight-hour outage. Essential controls and communications draw an assumed 12 kW continuously. Assume one pump runs at a time: a 60 kW pump block in hours 1–2, a 90 kW block in hours 4–5, and a 70 kW block in hours 7–8. These are exercise assumptions, not metered site data; the pump figures are additional to the 12 kW base load.
- Hours 0–1: 12 kW × 1 hour = 12 kWh.
- Hours 1–2: 72 kW (12 + 60) × 1 hour = 72 kWh.
- Hours 2–4: 12 kW × 2 hours = 24 kWh.
- Hours 4–5: 102 kW (12 + 90) × 1 hour = 102 kWh.
- Hours 5–7: 12 kW × 2 hours = 24 kWh.
- Hours 7–8: 82 kW (12 + 70) × 1 hour = 82 kWh.
The assumed duty totals 316 kWh and reaches 102 kW of running demand. Its average is 39.5 kW, which hides the 102 kW peak. The profile below shows the scheduled pump blocks against the continuous base load.

Check the starts, restoration and supply assumptions
The example assumes one pump at a time and counts running demand only. If pumps can start together during transfer or restoration, the pickup sequence and starting demand may change the duty; check equipment records and operating plans rather than adding an invented multiplier. Include the actual controls and auxiliary loads that the island must support.
Run separate cases when the outage duration or required service changes. A service that can pause for an hour may need a different interruption limit from one that must remain continuous. Check how long fuel, water, communications and other shared supplies support the selected case, and identify what happens if replenishment or site access is delayed.
Neither 102 kW nor 316 kWh alone sets the equipment rating. Verify the measured load boundary, pickup and transition requirements, electrical constraints, supply duration and performance evidence for each proposed configuration.
Compare resources against one load duty
Use the same outage case to compare storage, dispatchable generation or a combination: the service, interval-by-interval kW, accumulated kWh, permitted interruptions and dependencies should not change just because the equipment option does. The public Critical-Load Outage Worksheet and its blank fillable PDF help capture those inputs and evidence gaps. For the wider service boundary, see Distributed Generation Microgrid Planning for Utilities; for resource duties, see Batteries vs Generators for Microgrid Resilience.
Resilient Power Works works with utility teams to evaluate site-specific distributed-generation options; H2PWR Systems may be considered alongside alternatives once the site's load duty and requirements are defined. To discuss a utility application, email resilient-power-works@brainer.one with the site type, outage duration and non-sensitive load questions. Share sensitive infrastructure details only through an agreed secure channel.